Remaining connections to the hot water distribution will take place over the semester break and will include McNutt Hall, Straumanis James Hall, and Butler Carlton Civil Engineering Building. Also, hot water boilers in Toomey Hall will be installed and several HVAC renovation projects will be completed this summer. These projects include HVAC renovations in the Physics Building, Fulton Hall, Bullman Multi-Purpose Building, and Student Recreation Center. Once these are complete the geothermal system will be fully implemented.
When completed, the geothermal energy system is estimated to cut annual energy usage by 50%, reduce carbon dioxide emissions by 25,000 tons per year, and cut water usage by eight million gallons per year. Many parking and landscape improvements continue, the most recently completed being the landscaping improvements in the north mall area. Also occurring over the summer, parking lot 5 expansion north of Emerson Hall will be constructed.
Your continued patience is appreciated for any inconvenience caused from this phase of the project implementation as we move towards completion and a more energy efficient campus.
]]>We appreciate your patience during this period as we move towards a more energy efficient campus.
]]>
Circuit piping has been completed in all of the north lots and is well underway in well field 1, north of the Civil Engineering building. Paving in Lots #35, #29, #14 & #6 has been completed and parking opened to the campus. Lot #19 has been turned over to the University for parking lot reconstruction and the drive to the McNutt dock has been placed and has reopened to traffic.
Circuit piping has been completed in Lot #8, which will allow for the northern portion of Lot #8 to be reconstructed for additional parking in the north campus area. Drilling of the 195 wells in Lot #11 is now complete.
Lot #8 is scheduled to be back in service the week of September 17 and lot #36 will be taken out of service the same week.
]]>Summer:
When C 11 closes Area C permit holders may park in the following areas:
Fall:
See the updated construction schedule below. Please visit geothermal.mst.edu for more information regarding the geothermal project.
To view a full parking map for campus, click here.
If you are an Area L permit holder and you have not already, please notify parking of your alternate choice for parking: areas H, S, P or C. During the Summer (through 7/31/12) you can park in your current area until space is no longer available. At that time you can park in your alternate choice with your current sticker. If you have any questions please contact Parking Lot Operations at 341-4303. Further information will be provided as the project progresses. Thank you for your patience as we work towards a more energy efficient campus.
]]>To view a full parking map for campus, click here.